The President's Message
By Rick McClymont, Modular Building Institute
As a manufacturer/direct, Britco Structures has over the years been involved in some major building projects. The usual
format was for Britco to serve as a sub-contractor to a larger general contractor, although there have been occasions where
we contracted directly with end-users of modular buildings. Thankfully, most of our projects have gone smoothly with very
few problems. However, if a potential claim rears its head, manufacturers, dealers, and their customers would benefit greatly
by following the basics outlined in the following article by Grant Mayovsky and Douglas Sanders.
* * *
At the outset of any construction project, when goodwill and trust are usually at their high points, the parties will
often neglect to record in writing many of the key agreements and understandings reached between them. Later on in the
project, when problems start to arise, trust and goodwill often give way to the financial realities of potential construction
claims. More often than not, it is not until this latter point in time that the parties will start to thoroughly record events,
as well as any agreements and understandings that may have been reached.
Failure to properly record and document construction projects can be fatal in a claim. Written agreements and documentary
evidence will almost always outweigh oral evidence and alleged verbal agreements.
It is crucial to keep in mind the following items during the course of a project, which will help to support or defend a
claim should one arise:
- Keep all bid documentation and record any pre-contractual agreements, representations and understandings
in writing and ensure they are in the contract or can be relied upon at a later stage.
- Ensure that a fully signed written agreement is in place before commencing work on a project. While oral
agreements are generally enforceable, written ones are easier to prove.
- Read and be familiar with all contract terms, especially the notice provisions. Failure to provide
notification of a potential claim could preclude a party from bringing its claim.
- Keep all project correspondence. It is often helpful to organize project correspondence according to each
key party and whether the correspondence is incoming or outgoing. For example, it is important to remember that in order to
litigate a delay claim, it is generally necessary to reconstruct the project in detail on a daily basis.
- Record all relevant conversations and send follow up correspondence. Parties may proceed on a project for
months based on a particular representation or understanding, only to find out later during litigation that the other party
denies everything. Where there is no response to correspondence, a court may find that a failure to respond affirms what was
said in the letter.
- Take pictures or videos at all stages of the project. Nothing can help a judge or lawyer more to understand
a problem or deficiency on a project than an illustrative picture of it.
- Keep all plans and drawings and ensure that you have accurate records of all amendments or addendums.
- Make sure a project diary is kept along with diaries for key personnel. Diaries should record: 1) the
weather; 2) manpower, visitors and contractors on site; 3) key deliveries; and 4) any notable event such as problematic or hidden
site conditions or events that may cause delay or affect productivity. Ensure that entries express facts, rather than opinions.
- Maintain an as-planned schedule and regularly update it with an as-built schedule. There are several computer
programs available to schedule and track progress. The end product of a proper scheduling exercise is a plan that should tell a
contactor or owner what sequence work should be done in, when it should start, what work has to be completed first, when successor
activities should start, and when it should finish. Having an accurate schedule for a project and regularly updating it will
provide a valuable tool for tracking and recording delay and the impact of that delay.
- Record all key events, especially ones that may lead to a claim, and specifically record: 1) when the event
occurred; 2) what it was; 3) who noticed it; 4) the projected impact it may have on cost and time; 5) whether notice was given and
to whom; and 6) response to notice.
- Record all change orders and claims for extras and when they were submitted for approval, and separate those
that are approved from those that are not. A contractor who has failed to get approval for a change order should always diligently
express and protest their ongoing concerns writing. When doing so, the contractor should adhere to the contractual notice
requirements. Parties should also be aware of the ability to give notice that they are performing under protest.
- Document the additional costs caused by an event. It is particularly important to keep proper accounting and
employee payroll records pertaining to additional overhead and employee costs. Accounting records should be able to recreate the
costs associated with particular tasks and problems as well as to create a snap shot of costs incurred at a particular point in a
project.
- Finally, contact legal counsel as early as possible. Contractual interpretation and strategic decisions made
early can greatly enhance your prospects for success in a construction claim.
Rick McClymont is managing partner at Britco Stuctures in Surrey, British Columbia and president of the
Modular Building Institute.
Grant Mayovsky and Douglas Sanders serve the law firm Borden Ladner Gervais in Vancouver, British Columbia.
Copyright © Modular Building Institute, October 2003.
Additional Modular Building Articles
Modular Building Prices: A sampling of actual prices paid by modular building buyers who used our service can be found here, complete with purchasing details.
What's a Portable Classroom?: Today's modular building industry creates portable classrooms that are almost indistinguishable from site-built construction. Read more about the developments in this common field of construction.
Breaking Down Prefabricated Buildings: Using the same materials as traditional buildings, a manufacturer constructs prefabricated buildings in sections for easy transport and assembles the pieces at the customer's location.